Millville High School Greenhouse Lab Bid Notice

DOCUMENT 001113 - ADVERTISEMENT FOR BIDS

This Document uses the term "Architect."  Change this term to match that used to identify the design professional as defined in the General and Supplementary Conditions.

This Advertisement for Bids document is for use on public projects in conjunction with AIA Document A701, "Instructions to Bidders."  Coordinate content with the Instructions to Bidders.

Much of this Document consists of Project-specific data.  Examples given in the model document text below illustrate possible document content.  Use the model text to develop text for specific Project requirements.

1.1             PROJECT INFORMATION

Revise "Notice to Bidders" Paragraph below to comply with Owner requirements for notification and conduct of public bidding.

A.        Notice to Bidders:

BID NOTICE - Sealed proposals for "Millville High School – Greenhouse Lab” will be received at the administrative offices of the Millville Area School District, until 1:00 pm prevailing time on Thursday, February 3, 2022. Proposals will be publicly opened and read immediately following at the district offices (330 East Main Street, Millville, PA 17846).  A pre-bid meeting will be held on Thursday, January 27, 2022, 1:00 pm at the project site, 330 East Main Street, Millville, PA 17846.

Technical Questions may be addressed to Vertech Engineering Associates (e-mail: vertech303@verizon.net). Bidding Documents will be available from Strosser Baer Architects, Inc. (e-mail: andy@sba-arc.com) after 12 noon EST on Friday, January 14, 2022.   Drawings will be distributed electronically upon e-mail request.  Bidders shall be qualified, bondable contractors, with a minimum of five years of experience. Proposals shall be irrevocable for (90) days after bid opening, in compliance with Act #317 of 1978, approved November 26, 1978, and as amended, and shall be accompanied by 10% bid bond or certified check, payable to The Millville Area School District.

Project Scope of Work for the SINGLE PRIME CONTRACT; General Construction. Base Bid renovations include, but not limited to the following; Utility connections to the relocated Greenhouse Lab. Connections include domestic water, propane lines and electrical.

The project is subject to applicable provisions of the following, including any amendments and supplements:  Pennsylvania Prevailing Wage Act, Act of August 15, 1961, P.L. 987; Pennsylvania Human Relations Act of October 27, 1955, P.L. 744; Pennsylvania Public Works Contractor’s Bond Law of December 20, 1967, P.L. 869, no. 385.  A Performance Bond and a Labor and Material Bond for 100% of the project sum will be required. The Owner reserves the right to reject any or all bids and to waive, at its discretion, any or all irregularities, mistakes, or omissions.

END OF DOCUMENT 001113